Impact tolerance or recovery time objective?
A recovery time objective (RTO) sets how fast a system should return; an impact tolerance, when customer harm becomes intolerable. The RTO must sit inside it.
Two measures with different jobs
Firms often ask whether an impact tolerance is a recovery time objective, or RTO, under another name. It is not, and the impact tolerance RTO relationship is worth getting right. An impact tolerance is the maximum tolerable level of disruption to an important business service before harm becomes intolerable, measured by time and any other relevant metrics. An RTO is a recovery target, usually set for a system, an application or a process within business continuity and disaster recovery planning. The FCA put it simply in its 2024 insights and observations: a recovery time objective is the maximum time taken to recover the service.
Impact tolerances are a SYSC 15A duty. SYSC 15A.2.9R requires a firm to be able to remain within its tolerance in a severe but plausible disruption, and SYSC 15A binds only the firms in SYSC 15A.1.1R, and qualifying cryptoasset firms from 25 October 2027; every other firm has Principle 3, and our guide sets out who is in scope. Recovery planning reaches further. SYSC 4.1.8G, guidance that applies to most firms, says a business continuity policy should cover matters including the recovery priorities for the firm's operations and regular, proportionate testing. A firm outside SYSC 15A will usually have RTOs and no impact tolerances. The opening part of this cluster gives the full definition of an impact tolerance and its four defining features.
Why the RTO comes first and sits inside
CMORG's Guidance for Firm Operational Resilience, version 3 of April 2025, is industry guidance that CMORG says is voluntary and does not constitute regulatory rules or supervisory expectations. On this point it is direct. It says tolerances should not be confused with RTOs, because a tolerance is set in the context of intolerable harm while an RTO is set according to the firm's risk appetite. Because RTOs are objectives, it says they should be set before the tolerance, so that the goal is to recover before the tolerance is exceeded.
The FCA explained why the gap matters. In most cases, it said, processing still has to be done after services are recovered if intolerable harm is to be avoided, so it is common to see RTOs set well within impact tolerances. A system back online at its RTO with a day of unprocessed payments behind it has not restored the service customers rely on.
Fitting the RTO inside the impact tolerance
A practical way to check the fit is to lay out every step between the start of a disruption and a restored service, and time each one at peak demand:
- detecting the problem and recognising that it affects an important business service
- deciding to invoke recovery or a workaround
- recovering the systems, which is where the RTO sits
- checking that data is complete and accurate before processing resumes
- clearing the backlog built up during the outage
- telling customers the service is back
If the total exceeds the tolerance, the RTO is too long or the steps around it need work. Several RTOs may sit behind one service, and CMORG's mapping chapter notes that the recovery order of the critical systems behind a service is key to meeting tolerance thresholds. The slowest link in the chain sets the pace, not the average. The operational resilience guide shows how this connects to mapping and testing.
Recovery is not the only route
CMORG says a firm can stay within tolerance either by fully recovering the service or by mitigating action, such as workarounds or service substitution. The FCA's insights make the same point about response plans, which provide alternative actions during a disruption to buy time for recovery. That matters when an RTO cannot be shortened without heavy investment: a manual process or an alternative channel may keep the service within tolerance while the system is still down.
There is a limit. SYSC 15A.2.10G says a firm should generally not remain within its tolerance if doing so would increase the risk of harm to its clients or to the financial system, and that resuming a degraded service is usually only appropriate where the benefits outweigh keeping it unavailable. In PS21/3 the FCA gave the example of a service whose resumption could spread a computer virus, and said resuming a compromised service would not count as remaining within tolerance. An RTO met by restoring a compromised system is not a success.
Common gaps
- Tolerances copied from existing RTOs, which reverses the order CMORG describes. Our article on impact tolerances and scenario testing lists this among the weaknesses the FCA has seen most often.
- RTOs that measure system restoration only, with no allowance for data checks or backlog.
- One RTO per application with no view of how several applications combine behind one service.
- Recovery commitments agreed with suppliers that nobody has compared with the tolerance of the service they support.
Related: Writing an impact tolerance statement; Risk appetite versus impact tolerance.
What to do
- For each important business service, list the systems and suppliers behind it with the RTO of each.
- Map the steps from detection to restored service and time each one at peak demand.
- Confirm that the total sits inside the tolerance with a margin, and record the margin.
- Where it does not, shorten the RTO, change the recovery order or add a tested workaround.
- Compare supplier recovery commitments with the tolerance, not only with the contract.
- Test the chain end to end, including data checks and backlog clearance.
Our view
In our view the RTO is an engineering commitment and the impact tolerance is a customer commitment, and the first exists to serve the second. When a firm finds the two set at the same figure, it usually means the tolerance was worked backwards from what technology could already deliver.